Cliff Road Rehabilitation

Posted on: June 8, 2018

Cliff Road Reconstruction 6/6/2018

The drainage work is now complete.  The contractor, Perkins, will begin the sidewalk work on Monday June 11.  We have asked the contractor to begin work on the northerly side of the roadway, which will take approximately 1 month to complete.  This work includes removing the existing asphalt and concrete sidewalks, extending the sidewalk to White Oak Road and paving with asphalt.  The sidewalk will also include a strip of treelawn in front of the sidewalk, separating the sidewalk from the roadway.

It is our intent to minimize the disruption of your normal routines as best we can. If you have any questions, at any time during the duration of the project, feel free to call the DPW Engineering Division at 781-235-7600, extension 3315.
Thank you for your patience