Cliff Road Reconstruction Project Update - July 6, 2018

The Department of Public Works would like to provide an update on the Cliff Road Roadway Improvements Project construction.  The road surface is scheduled to be milled; a process of removing 2-inches of asphalt, with a pavement milling machine, a...

Read on...

Cliff Road Rehabilitation
Posted on: June 27, 2018

Cliff Road Reconstruction Update 6/27/2018

To date, storm drainage improvements have been completed and sidewalk replacement work is approximately 50% complete.  Over the next few weeks, sidewalk replacement work will continue and wheelchair ramp reconstruction at sidewalks and crosswalks...

Read on...

Cliff Road Rehabilitation
Posted on: June 8, 2018

Cliff Road Reconstruction 6/6/2018

The drainage work is now complete.  The contractor, Perkins, will begin the sidewalk work on Monday June 11.  We have asked the contractor to begin work on the northerly side of the roadway, which will take approximately 1 month to compl...

Read on...

Cliff Road Rehabilitation
Posted on: May 4, 2018

Cliff Road Roadway Improvements Project

The Cliff Road Roadway Improvements Project is scheduled to commence on May 10, 2018. The work will take place on Cliff Road between Route 9 and the Town Line.  Work will take place Monday through Friday between the hours of 9:00 AM and 4:00 PM. ...

Read on...