Brook and Benvenue Streets Intersection Improvement
September 27, 2019
7 AM - 5 PM
Final roadway paving is planned for the Brook Street & Benvenue Street Intersection Improvement project. On Friday, September 27, the intersection area will be closed from 7 a.m. to 5 p.m. Detours will be in place for Brook Street, Benvenue Street and Radcliffe Road; drivers may experience slight delays.
Wellesley Police officers and DPW staff will be on-site to direct traffic through these detours. The intersection will re-open once work is completed.
August 14, 2019
7 AM - 5 PM
Final roadway paving is planned for the Brook Street & Benvenue Street Intersection Improvement project. On Friday, September 27, the intersection area will be closed from 7 a.m. to 5 p.m. Detours will be in place for Brook Street, Benvenue Street and Radcliffe Road; drivers may experience slight delays.
Wellesley Police officers and DPW staff will be on-site to direct traffic through these detours. The intersection will re-open once work is completed.
August 14, 2019
The Department of Public Works (DPW) continues work on the Brook Street & Benvenue Street Intersection Improvement Project. The project will reconfigure the Brook Street, Benvenue Street and Radcliffe Road intersection. Removal of the traffic island, relocating utility pole and storm drainage improvements are almost completed. Work over the next few weeks will include completion of storm drainage improvements, pavement milling and preliminary work on sidewalks and curbing.
Please note road detours will continue to be in place to accomplish the work in the intersection area. Detours and detour signage will be setup for the intersection and surrounding area, with limited access through the intersection area. Police officers and DPW staff will be on site to assist with detours.
Work will take place Monday through Friday between 7:00 AM and 5:00 PM. Police details will be on-site during construction to minimize impacts to traffic, parking, and other roadway functions. The work is scheduled to be completed in October 2019.
June 26, 2019Please note road detours will continue to be in place to accomplish the work in the intersection area. Detours and detour signage will be setup for the intersection and surrounding area, with limited access through the intersection area. Police officers and DPW staff will be on site to assist with detours.
Work will take place Monday through Friday between 7:00 AM and 5:00 PM. Police details will be on-site during construction to minimize impacts to traffic, parking, and other roadway functions. The work is scheduled to be completed in October 2019.
The work will be accomplished by I.W. Harding Construction Co., Inc. and their subcontractors, under the direction of the Town of Wellesley Department of Public Works. The work is scheduled to be completed in October.
Work will take place Monday through Friday between the hours of 7:00 AM and 5:00 PM. Police details will be on-site during the project construction to minimize impacts to traffic, parking, and other roadway functions. A minimum of one lane of traffic in each direction will be maintained throughout the majority of the project.
It is our intent to minimize the disruption of your normal routines as best we can. If you have any questions, at any time during the duration of the project, feel free to call the DPW Engineering Division at 781-235-7600, extension 3315.