Project Updates

August 2020 Update: 

Scheduled project work for the next two weeks, starting on August 10, 2020 includes: completing erosion control measures, tree removal work, excavation of test pits and installation of the stormwater drainage system. Police details will be on site to assist with traffic control through the project work site area.