Resurfacing Notices

Resurfacing Notice Friday-Wednesday, October 8, 9, 12, &13

Woodchester Road
Paving Complete 10/8/21 


Oakcliff Road
Paving Complete 10/8/21 


Edge Hill Road
Paving Complete 10/8/21 

Surrey Lane

Paving Complete 10/13/21

Glen Brook Road

Paving Complete 10/12/2021



Rockland Street
Paving Complete 10/8/21 

Audubon Road

Paving Complete 10/9/21

Cranmore Road

Paving Complete 10/9/21

Salem Road

Paving Complete 10/12/21

Scotch Pine Road

Paving Scheduled 10/12/21


Hampshire Road

Paving Complete 10/13/21

Pine Plain Road
Paving Complete 10/7/21 



Final resurfacing is complete on the roads listed below, as of Wednesday, October 6th.  

Check back here or our twitter feed @wellesleydpw for live DPW updates. 

Letter from Director explaining Cape Seal Resurfacing Process

Arlington Road
Paving Complete 10/6/21 

Ayer Road
Paving Complete- 10/1/21

Beverly Road

Paving complete - 10/1/21

Deerfield Road

Paving complete - 10/1/21

Greenbough Lane
Paving Complete 10/6/21

Pleasant Street

Paving complete - 10/1/21

Radcliffe Road
Paving Complete 10/6/21

Roberts Road

Paving complete - 10/1/21

Shelburne Road

Paving complete - 10/1/21

Skyline Drive
Paving Complete 10/6/21 

Wall Street
Paving Complete  10/1/21



***Turn off Sprinkler Systems***

The Town contractor is scheduled to be in the neighborhood's listed above. On the day of resurfacing, there will be no parking on the roadway after 7:00 am until all of the work is completed. After the resurfacing and rolling process, the street should be open for normal traffic within 2 hours. Please make all attempts to avoid sharp turning of vehicle tires on the new surface for approximately 24 hours.

                                                                                                                                                                                                

Cold Planing will occur at the following locations on Saturday, October 2nd, Monday, October 4th, and Tuesday, October 5th. Signs will be posted on your street the afternoon before work is to be completed. Paving is expected later this week and we will update this information when the schedule is confirmed.


Woodchester Road
Milling Completed 10/2



Hampshire Road
Milling In Progress 10/4



Audubon Road
Planned for 10/4 & 10/5


Rockland Street
Planned for 10/4 & 10/5

The Town contractor is scheduled to be in the neighborhood's listed above. There will be no parking on the roadway after 7:00 am until all of the work is completed. After the grinding and sweeping process, the street will be open for normal traffic. When milling is complete the roadway will be rough and the structures (manhole & catch basin frames, water gates, etc.) will be raised. Please use caution when traveling on the roadway until the final pavement has been installed. The roadway will be paved as soon as our contractor can schedule the work.

While it is our intention to complete this work on the day indicated, weather or equipment problems may cause the work to be delayed, in which case it will be done the following day or as soon as possible thereafter. No Water can be present on the roadway from rain, sprinkler system, washing cars, etc.

We apologize in advance for any inconvenience that you may experience during this process, and hope you will enjoy these improvements to your neighborhood once they have been completed. Any questions concerning the work should be directed to the Highway Division at 781-235-7600 x3325.